| Procuring Authority / Buyer | SH.A Ujesjelles Kanalizime Cerrik | ||||||||||
| Procuring Authority / Buyer | Local Unit Cërrik | Tender object | Rikonstruksione të linjave të brendshme të rrjetit të ujësjellësit të Sh.a.UKC | ||||||||
| Reference No. | REF-38173-12-14-2017 | ||||||||||
| CPV Code | |||||||||||
| Estimated / Ceiling Value ALL without VAT | 7 387 169,00 | ||||||||||
| Type of Contract | |||||||||||
| Procurement Method | Request for Proposal | ||||||||||
| Stage Procedure | Signed the Contract | ||||||||||
| Tender Publication Date | 15-12-2017 | ||||||||||
| Last date of Submitted Documents | 26-12-2017 | ||||||||||
| Tender Held Date | 26-12-2017 | ||||||||||
| No. of Bidders | 4 | ||||||||||
| Bidders |
Blerimi Shpk Colombo Shpk IMAG Shpk & BELADI Shpk Viante Konstruksion Shpk |
||||||||||
| Successful Bidder /Supplier / Provider |
|
||||||||||
| The winning bid ALL without vat | 6 943 526,00 | ||||||||||
| Bidder Announcement date | 17-01-2018 | ||||||||||
| Award and Contract Amount ALL with VAT | 8 332 231,00 | ||||||||||
| Contract date | 23-01-2018 | ||||||||||
| Planned Milestones of Contract / Start and End Date | 22 ditë | ||||||||||
| Renewal Contract Additional Value (ALL with VAT) | |||||||||||
| Appeals |
Nuk ka pasur ankesa Janë skualifikuar ofertuesit e mëposhtëm: 1. Colombo sh.p.k - Per arsyet e meposhtme: Operatori ekonomik nuk e ploteson kushtin per Kapaciteti teknik kontrata te ngjashme te se njejtes natyre. 2. IMAG sh.p.k & BELADI sh.p.k IMAG sh.p.k & BELADI sh.p.k - Per arsyet e meposhtme: IMAG sh.p.k & BELADI sh.p.k - Per arsyet e meposhtme: Ne akt-marreveshjen ndermjet shoqerive percaktohet vetem perqindja e ndarjes se punimeve dhe jo ndarja sipas elementeve konkrete te punimeve. 3. Viante Konstruksion sh.p.k - Per arsyet e meposhtme: Nuk ka paraqitur një kopje të Ekstraktit mbi historikun e subjektit të lëshuar nga Qendra Kombëtare e Regjistrimit. |
||||||||||
| Cancellation reason | |||||||||||
| Additions | |||||||||||